AT A GLANCE

 

99.98%

Average System Availability (ASAI)

Strategic Goal: 99.95%


0

Miles of Electric Right of Way Maintained


74%

Work Order Completion (Electric, Monthly)

Goal:  Within 7 Days


80%

Work Order Completion (Water & Sewer, Quarterly)

Goal: Within 7 Days



 

 

 

 Utilities Header

October 2018

Water Filter Plant
2102 Cherry Road
Treatment Capacity—36MGD

 Water Chart Oct 2018

Manchester Creek Wastewater Treatment Plant
310 Red River Road
Treatment Capacity = 20 MGD 