Residential Inspections

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Request inspections through the button below. Most inspections can be completed the same day if entered into the portal before 7 a.m.

Separate Submittals

You must submit plans and receive permits for all other required submittals that were not included in the building plans, such as fences, retaining walls, irrigation systems, pools, and detached garages and accessory buildings. Those inspections will be completed separately from the below list.

Prior to the First Inspection

You must have the following in place prior to the first inspection, and these items must remain in place for the duration of the project:

  1. The address and a copy of the approved building permit must be posted visibly from the road in an accessible, waterproof enclosure.
  2. Approved stamped plans must be on-site for the duration of the project. The City’s approval letter or conditional approval letter, and a copy of the issued permit that lists all conditions must be attached to the front of the stamped plan set.
  3. Toilet facilities must be available within 300 feet of the job site.

Erosion control measures

Wait to put erosion control measures into place until after your preconstruction meeting has occurred.

  1. A construction entrance and driveway that is at least 10 feet by 25 feet must be in place prior to starting construction. The driveway may consist of gravel if it is at least 6 inches thick with No. 4 stone (two to three inches in diameter).  
  2. Provide barricades such as silt fence or orange barricade fencing to prevent suppliers or subcontractors from driving onto the lot without using drive. All deliveries to the lot must be made via the driveway, and no other vehicles should be driven onto the site.
  3. Install silt fence along the low spots on the property and along all lower adjacent properties. Ensure that the fence is intact and functioning at the end of each day. Wire-backed silt fence must be used when contributing slope exceeds 3%.
  4. If mud is carried into the street by vehicles, it must be swept up at the end of the workday. Do not wash/hose down unless proper inlet protection measures are in place.
  5. For proper application, installation and maintenance of sediment and erosion control measures, please see SCDES’s Sediment Control Standards Details (PDF).

Have utility lines marked

Request that all utility providers come mark the location of utilities at least 3 full business days before you dig. This is required by state law and is a free service.

Required Inspections and Documentation

1. Footing Inspection
2. Underslab Plumbing Inspection
3. Slab and Crawlspace/Underfloor Inspection
4. Elevation Certificate for Building Under Construction (if in flood hazard area)
5. Open Floor Inspection
6. Exterior Sheathing Inspection
7. House Wrap
8. Framing All Roughs Inspection (including Energy Code requirements)
9. Firewall Inspection
10. Insulation and Energy Code Inspection
11. Request Underground Power
12. Temporary Power Inspection
13. Energy Code Compliance Tests (if not verified at Framing All Roughs stage)
14. Elevation Certificate for Finished Construction (if in flood hazard area)
15. Final Inspections

Other Information

Change Orders
Reinspection Fees
Open Burning
Change of Superintendents

Infrastructure Inspections

We have a separate webpage with information about infrastructure inspections for both residential subdivisions and non-residential developments.

Special Inspections

When required by the building code, special inspections reports must be submitted and approved by the City prior to the issuance of a Certificate of Occupancy. Special inspections are rare for single-family construction but are required for retaining walls. 

Commercial Building Inspections

Commercial, industrial, institutional and multi-family developments should use the information on our Commercial Inspections webpage.